Decision Engine — Tool 04

Timeline to Operation Estimator.

From LOI signed to first commercial shipment — a phased timeline with critical-path callouts. The shelter and standalone paths share most milestones but front-load very differently. v1 surfaces the differential and names the longest pole on each side.

Benchmarks

Atlantis & SUMMA engagements

10 phases · 1979–present · Reviewed: 2026-05-01

Statutory anchors

SAT · Secretaría de Economía · CFE

RFC issuance norms · IMMEX certification windows · CFE interconnection ranges. Phase ranges calibrated against current regulator timelines.

Access

Open · No qualification

Educated estimates calibrated to typical engagements. Your timeline depends on site, sector, and counterparty execution.

Real estate posture
Capex intensity

Shelter path

22 weeks

First shipment ≈ Oct 8, 2026

Standalone path

44 weeks

First shipment ≈ Mar 11, 2027

Differential

+22 weeks

Standalone takes 22 weeks longer.

Shelter path

Critical-path pole: Equipment install and commissioning (8 wks)

0w4w8w12w16w20w24w28w32w36w40w44w1. LOI signed → engagement kickoff2w2. Site selection and lease/build…4w3. Mexican entity formation (SAT …— absorbed by shelter umbrella —4. IMMEX certification5w5. Real estate (lease execution o…2w6. Utility installation (power, w…3w7. Permits (municipal, state, env…3w8. Equipment install and commissi…8w9. Workforce hire and train6w10. Pilot run → ramp → first comme…3w

Equipment install and commissioning is the most common pole for shelter engagements once site and entity questions are absorbed by the shelter operator.

Standalone path

Critical-path pole: Utility installation (power, water, gas) (12 wks)

0w4w8w12w16w20w24w28w32w36w40w44w1. LOI signed → engagement kickoff2w2. Site selection and lease/build…8w3. Mexican entity formation (SAT …6w4. IMMEX certification11w5. Real estate (lease execution o…6w6. Utility installation (power, w…12w7. Permits (municipal, state, env…8w8. Equipment install and commissi…11w9. Workforce hire and train9w10. Pilot run → ramp → first comme…5w

Real estate delivery (especially build-to-suit and greenfield) and CFE interconnection are the two most common standalone-path poles.

Critical path
Off critical path (slack)

Counted from LOI signed today (May 7, 2026).

Methodology and what v1 does not model

A standard 10-phase Mexico nearshoring sequence with explicit dependencies. Critical path computed forward and backward; phases on the critical path render in amber. Every phase carries a low/mid/high range — v1 displays mid-point durations and adjusts two phases (real estate, equipment) to user-selected posture.

In v1

Real-estate posture and capex intensity as adjustable inputs. Shelter vs. standalone shown side-by-side. Critical-path math and longest-pole callouts. Today as the LOI date, with first-shipment dates rendered live.

v1 does NOT model

Sector cycles, counterparty execution, exogenous shocks

Sector-specific permit cycles (medical-device cleanrooms, semiconductor fabs, automotive Tier 1 PPAP), counterparty-driven schedule slip, equipment lead-time spikes, currency or political shocks, force majeure. Heavy-industry projects routinely run high or above the high range. Light-assembly shelter projects routinely beat low.

v2 — sector and state overlays

Sector regulatory profile, state permitting velocity, headcount band

Sector-driven adjustments to permits and ramp; state-driven adjustments to permitting and CFE interconnection; headcount-driven adjustments to workforce ramp. Backed by the per-region engagement data Atlantis carries on the regions section.

v3 — uncertainty bands

Low/high envelope rendered on the chart

Each phase already carries a low/mid/high range in the underlying data. v3 renders the envelope as a band per phase so users see schedule risk visually, not as a single-point estimate.

Adjacent reading